Tuesday, May 12, 2026

Harbor Medical Pavilion · prepared by T. Calloway (Super)

Weather

Partly cloudy, 60–76°F

Crew on site

71

Photos

14

Trades

3

Trades on site

MEPCeiling gridDoor installer

Work performed

Door frames set on 4th floor — patient rooms and back-of-house. Lead-lined door delivered for imaging suite. MEP coordination meeting held 10 AM.

Delays / issues

Lead-lined door for radiology delivered 1 week late. No impact — schedule slack absorbed.