Daily Reports
4 reports on file. Average time-to-PDF: 42 seconds.
Thursday, May 14, 2026
SentBy T. Calloway (Super)
Sunny · 62–78°F84 workers27 photos
OR suite 3 fitout continuing — medical gas rough-in approved. Ceiling grid set in west corridor. Sheet vinyl flooring installed in patient rooms 412–418.
MEPDrywallCeiling gridFlooring
+23
Wednesday, May 13, 2026
SentBy T. Calloway (Super)
Sunny · 64–80°F79 workers19 photos
Wall tile set in patient room wet walls 401–411. Painting continues in corridors. Med gas rough-in OR suite 2 complete and pressure-tested.
MEPDrywallTilePainting
+15
Tuesday, May 12, 2026
SentBy T. Calloway (Super)
Partly cloudy · 60–76°F71 workers14 photos
Door frames set on 4th floor — patient rooms and back-of-house. Lead-lined door delivered for imaging suite. MEP coordination meeting held 10 AM.
MEPCeiling gridDoor installer
+10
Lead-lined door for radiology delivered 1 week late. No impact — schedule slack absorbed.
Monday, May 11, 2026
SentBy T. Calloway (Super)
Rain · 58–68°F54 workers8 photos
Indoor work only — MEP rough-in on 5th floor, drywall hang on 4th. Site logistics slowed by rain.
MEPDrywall
+4