Daily Reports
3 reports on file. Average time-to-PDF: 42 seconds.
Thursday, May 14, 2026
SentBy M. Reyes (Super)
Partly cloudy · 58–72°F47 workers18 photos
Concrete pour completed on level 14 deck (slab edge to column line G). Steel erection continuing on levels 16–18. MEP rough-in proceeding floors 8–10. Drywall hanging on floors 3–4.
ConcreteSteelMEP rough-inDrywall
+14
Crane #2 down for inspection until 10:30 AM, recovered by EOD.
Wednesday, May 13, 2026
SentBy M. Reyes (Super)
Clear · 60–75°F52 workers22 photos
Forms set for level 14 deck. Steel beams erected at level 17. Plumbing risers continuing.
ConcreteSteelMEP rough-in
+18
Tuesday, May 12, 2026
SentBy M. Reyes (Super)
Light rain AM · 52–64°F38 workers11 photos
Concrete pour postponed due to morning rain. Indoor work continued — drywall and MEP rough-in.
SteelMEP rough-inDrywall
+7
Concrete pour pushed to 5/14. No critical-path impact.