RFI-042sentto SHoP Architects
Conflict between mechanical duct and beam at column line G/14
Level 14, Grid G/14
During MEP rough-in coordination, a conflict was identified between the 24x14 supply duct (M2.14) and the W18x40 beam at column line G/14. Routing per drawings shows the duct passing through the structural depth of the beam. Please advise on revised routing or beam penetration.
Created May 12, 2026
RFI-041answeredto SHoP Architects
Curtain wall anchor detail at parapet — missing dimensions
Roof level, all faces
Detail 7/A8.21 references a 'standard parapet anchor' but does not provide spacing or anchor type. Please confirm anchor schedule.
Created May 8, 2026
RFI-040closedto SHoP Architects
Fire-rated assembly for corridor 1A on level 3
Level 3, Corridor 1A
Spec section 09 21 16 calls for 2-hour rating, but plan A2.03 wall tag shows 1-hour. Please clarify rated assembly.