Chalkline
JK
ProjectsMidtown Tower

Submittal Log

Midtown Tower · 16 total · 8 approved · 3 critical-path open

Total

16

Approved

8

Under Review

3

Submitted

2

R&R

1

Not started

2

3 critical-path submittals still open — these affect schedule if not resolved.

Showing 16 of 16

Section
Item
Type
Lead
Status
Last action
03 30 00

Concrete mix designs (all strengths)

Cast-in-Place Concrete · Roman Concrete Co.· Critical path

Quality Control
21 days
Approved Oct 18
03 30 00

Reinforcing steel shop drawings

Cast-in-Place Concrete · Roman Concrete Co.· Critical path

Shop Drawings
28 days
Approved Oct 29
05 12 00

Steel shop drawings — Erection plans

Structural Steel · Atlas Steel Fabricators· Critical path

Shop Drawings
42 days
Submitted Apr 22
05 12 00

Mill certifications — Wide flange

Structural Steel · Atlas Steel Fabricators

Product Data
14 days
Approved Mar 18
05 12 00

Welder qualifications (AWS D1.1)

Structural Steel · Atlas Steel Fabricators

Quality Control
14 days
Submitted May 9
07 21 00

Mineral wool batt product data

Thermal Insulation · Northside Insulation

Product Data
10 days
Approved Feb 19
07 95 00

Seismic joint cover system

Expansion Control · Apex Specialties

Product Data
21 days
Submitted Apr 30
09 21 16

Gypsum board product data

Gypsum Board Assemblies · Citywide Drywall

Product Data
10 days
Approved Jan 22
09 21 16

UL fire-rated assembly cut sheets (U411, U419, U467)

Gypsum Board Assemblies · Citywide Drywall

Product Data
14 days
Approved Jan 22
09 30 00

Porcelain tile samples — Restrooms

Tiling

Sample
21 days
Due in 21d
23 21 00

Chilled water piping shop drawings

Hydronic Piping · Citywide Mechanical· Critical path

Shop Drawings
35 days
Submitted May 12
23 00 00

Air-cooled chiller cut sheets (2 ea, 250 ton)

HVAC General · Citywide Mechanical· Critical path

Product Data
21 days
Approved Mar 25
23 00 00

VAV box submittals

HVAC General · Citywide Mechanical

Product Data
14 days
Submitted May 1
26 00 00

Switchgear shop drawings

Electrical General · Borough Electric· Critical path

Shop Drawings
56 days
Submitted Apr 15
26 00 00

Light fixture cut sheets

Electrical General

Product Data
21 days
Due in 21d
26 32 13

750kW diesel generator product data

Engine Generators · Borough Electric· Critical path

Product Data
84 days
Approved Jan 8