All meetings
Subcontractor coordination
Subcontractor coordination — MEP/Structural
Friday, May 8, 2026
Attendees
M. Reyes (GC Super)D. Whitfield (Atlas Steel)F. Romero (Citywide Mechanical)K. Patel (PM, GC)
Decisions
- Steel erection sequence on Level 16-18 to proceed before MEP rough-in on those floors.
Discussion
Sequencing on Levels 16-18
Confirmed steel erection priority. MEP to stay one floor behind once steel reaches Level 19.
Welding hot-work permits
Atlas to coordinate hot-work permits daily with GC fire-watch. New form to be used starting Monday.
Action items