Subcontractor coordination

Subcontractor coordination — MEP/Structural

Friday, May 8, 2026

Attendees

4

Action items

0 open / 2 total

Next meeting

Not scheduled

Attendees

M. Reyes (GC Super)D. Whitfield (Atlas Steel)F. Romero (Citywide Mechanical)K. Patel (PM, GC)

Decisions

  • Steel erection sequence on Level 16-18 to proceed before MEP rough-in on those floors.

Discussion

  • Sequencing on Levels 16-18

    Confirmed steel erection priority. MEP to stay one floor behind once steel reaches Level 19.

  • Welding hot-work permits

    Atlas to coordinate hot-work permits daily with GC fire-watch. New form to be used starting Monday.

Action items

Submit revised MEP rough-in look-ahead schedule.

F. Romero (CM)

2026-05-12

Issue new hot-work permit form to all welding subs.

M. Reyes (Super)

2026-05-11