Sunday, May 10, 2026
Pre-CO punch — Levels 3-4 corridors
Levels 3-4 (corridor & common areas) · walked by K. Patel (PM)
Total
5
Open
3
In progress
1
Closed
1
Critical open
1
1 critical item still open — close before turnover.
Level 3, Corridor 1A near elevator lobby
Drywall
Drywall corner bead crushed, joint mud cracked over 2-ft section.
→ Repair bead, re-tape & finish to Level 4.
Level 3, Unit 312 entry door
Doors / hardware
Closer not adjusted — door slams shut.
→ Adjust closer to manufacturer spec.
Level 4, Corridor near stair B
Painting
Paint flash at wall-to-ceiling joint. Roller marks visible.
→ Sand, prime, and re-coat the joint area.
Level 4, Unit 402 bathroom
Tile
Chipped corner on shower bench coping. Sharp edge.
→ Replace coping piece. Safety risk — flag for completion before turnover.
Level 4, Corridor ceiling at Grid C/8
Ceiling grid
ACT panel cut short by ~1/4", visible gap.
→ Replace cut panel.