Sunday, May 10, 2026

Pre-CO punch — Levels 3-4 corridors

Levels 3-4 (corridor & common areas) · walked by K. Patel (PM)

Total

5

Open

3

In progress

1

Closed

1

Critical open

1

1 critical item still open — close before turnover.

#1

Level 3, Corridor 1A near elevator lobby

Standard

Drywall

Drywall corner bead crushed, joint mud cracked over 2-ft section.

Repair bead, re-tape & finish to Level 4.

#2

Level 3, Unit 312 entry door

Minor

Doors / hardware

Closer not adjusted — door slams shut.

Adjust closer to manufacturer spec.

#3

Level 4, Corridor near stair B

Standard

Painting

Paint flash at wall-to-ceiling joint. Roller marks visible.

Sand, prime, and re-coat the joint area.

#4

Level 4, Unit 402 bathroom

Critical

Tile

Chipped corner on shower bench coping. Sharp edge.

Replace coping piece. Safety risk — flag for completion before turnover.

#5

Level 4, Corridor ceiling at Grid C/8

Minor

Ceiling grid

ACT panel cut short by ~1/4", visible gap.

Replace cut panel.