Daily Reports
2 reports on file. Average time-to-PDF: 42 seconds.
Thursday, May 14, 2026
SentBy D. Olsen (Super)
Clear · 50–70°F22 workers11 photos
Site mobilization complete. Erosion control installed. Mass excavation started in northwest quadrant. Crusher delivered for on-site material processing.
Site WorkDemolition
+7
Wednesday, May 13, 2026
SentBy D. Olsen (Super)
Clear · 48–68°F18 workers6 photos
Stake-out of building pad complete. Survey verified to drawings. Pre-construction conference with subs at 2 PM.
Site Work
+2