Chalkline
JK
ProjectsNorthgate Distribution Center

Submittal Log

Northgate Distribution Center · 5 total · 0 approved · 3 critical-path open

Total

5

Approved

0

Under Review

0

Submitted

1

R&R

0

Not started

4

3 critical-path submittals still open — these affect schedule if not resolved.

Showing 5 of 5

Section
Item
Type
Lead
Status
Last action
31 23 00

Geotechnical engineer site-observation reports

Excavation and Fill · ProGeo Engineers· Critical path

Quality Control
7 days
Submitted May 13
03 30 00

Slab-on-grade concrete mix designs

Cast-in-Place Concrete· Critical path

Quality Control
14 days
Due in 14d
05 12 00

Pre-engineered metal building shop drawings

Structural Steel· Critical path

Shop Drawings
56 days
Due in 56d
07 41 13

Standing-seam roof panel system

Metal Roof Panels

Product Data
35 days
Due in 35d
11 13 13

Dock levelers and seals (14 ea)

Loading Dock Equipment

Product Data
42 days
Due in 42d