RFIs
2 requests on file. Average time-to-draft: 31 seconds.
RFI-002sentto Ware Malcomb
Dock leveler quantity for west elevation
Drawing A1.1 shows 12 dock levelers on west elevation; spec section 11 13 13 calls for 14. Please confirm.
Created May 13, 2026
RFI-001answeredto Ware Malcomb
Mass excavation — unsuitable soil bearing
Northwest quadrant
Surveyor identified soft material at 3' below grade in NW quadrant — geotech bearing minimum 3,000 psf not achievable. Please advise on overexcavation extent.
Created May 12, 2026